Traffic Advisory:  US 68 (Broadway) In Campbellsville 

A project to resurface a three-mile stretch of US 68 (Broadway) through Campbellsville is scheduled to start next week. Crews will begin with milling on Monday, June 15th, between KY 210 (Hodgenville Road) and KY 1799 (Airport Road). Milling of the surface will take approximately one week. Paving will begin once all milling is complete. The paving phase of work will take approximately two weeks. The work schedule is weather dependent. 

Motorists need to be aware of daily lane closures, temporary side road closures and flagging operations. Expect congestion and delays. 

Slow down though the work zone, pay attention to signs, workers and equipment. Use an alternate route, if possible, especially during peak morning and afternoon traffic. 

(Chris Jessie, Public Information Officer – KYTC District 4)